Tuesday, July 24, 2012

The Water Line - The Final Ditch

The final mission of our site work was getting the water line in the ground from the studio to the well, which is a distance of about 200 feet. Unfortunately, the only path for this line was along the side of the driveway, which is finally getting compacted. Rob spent the last couple days digging the required 4 feet deep ditch (to be below the frost line) and putting in the water line in a protective pipe as he went. Last night, I helped him pull the line through the final 30 feet. Then we jumped in the lake to wash off!




The wood "T" is 4 feet high so Rob knows how deep to dig



The line finally reached the well (green capped structure on the left) at 8 pm last night!



Wednesday, July 18, 2012

Backfilling - Updated

As of a month ago, I didn't know what the term "backfilling" meant, but it's become a prominent part of our vocabulary lately. We got the okay last week from the building inspector to backfill around the foundation, and from the engineer and board of health inspector to backfill the septic system. So, what does that word mean anyway? It basically means putting the soil that was removed back in place. Rob's spent the last few days backfilling the upper portion of the septic system (first pic below) and around the foundation, i.e. putting the hill back that we dug out for the foundation.

The stakes show the location of the septic tank, and all the connecting pipes are now covered up. Hoping to fill this area in with a small stream and native ferns and shrubs.

In the middle of the backfilling process

After it rained on Sunday, the area turned into a muddy mess

Here's the hill back in place

This is the backside (west side) of the building backfilled

West side from behind a locust tree
Northeast corner before backfilling

Northeast corner with fabric (goes between stone and soil)

North side after backfilling

Another view of the north side after backfilling
Deer Print - Our deer friends are still using the area, although they've made some new paths on the upper lot, which they seem to be using more

After backfilling around the foundation, Rob backfilled the leach field, which is now just an open field of soil - future garden? 

We also created a hang out spot with our hammocks - we especially like the new one we got from Judy and Lance (the one Rob is in)!
 


Friday, July 13, 2012

The Foundation: Waterproofing and the Slab

This week began with the headache of trying to track down our waterproofing materials which had been ordered by ABC Supply from the CCW factory in Carlisle, PA. After a series of conversations with Mike from ABC who managed to botch up the delivery last Friday, I was considering driving down to Carlisle to pick up the supplies myself as Mike could not assure me of the delivery day/time, and we needed to get the waterproofing done by Thursday (before the building inspector left for vacation for a week). Mike convinced me with a tracking number that the materials were on their way. However, Tuesday morning, there was still no sign of the materials and Mike revealed that he had been given the wrong tracking number. I decided to rent a pick-up truck and drive down to Carlisle myself - a four hour drive each way - to pick up the supplies.




Meanwhile, Rob was working like mad to prepare the foundation for the floor to be poured on Friday (today!). This involved bringing in stone to the top of the footings and laying insulation for under the slab - 2" XPS foam - R-value = 5/inch (for those interested in our green features). In addition, a piece of 6 ml plastic had to be laid over the insulation as a vapor barrier. Our neighbors Justin and Michael were a huge help!





The next morning (Wed) with the help of our neighbor Justin, we began the process of applying the waterproofing materials (really a whole system). Step 1: Rob and I first applied a primer (CCW 702 WB) to the walls by rolling/painting it on, which got sticky after half an hour. Step 2: After this, Rob and Justin applied mastic (a type of putty-type caulking - CCW 800XL) at the junctures between the walls and the footings - green stuff in the pictures below. Step 3: After that settled for an hour, we began the tedious process of applying the sheets of waterproofing (CCW 860), which had an adhesive on the back which stuck to the primer on the walls. Eventually, Rob, Justin, and I got a system down so that we could apply the sheets without getting it all stuck together in the wrong places. We worked until 9 pm to get this done.

Step 1: The primer after we painted it onto the walls

Step 2: Caulking and Coffee

Step 3: The Waterproofing Sheets

Step 3 also: Rob, Justin, and I crouched in the corner applying waterproofing after dinner!   
Our neighbor Keb drove over to check out the waterproofing

Also on Wednesday, Van's crew came to lay the wiring for the foundation floor (4" concrete slab) which needed to be inspected on Thursday and poured on Friday.



On Thursday morning, Rob and I got an early start at finishing the difficult spots with the waterproofing - our neighbor Julie came to help with this as well. The building inspector came at 11 am to inspect the waterproofing and the wiring for the floor. He gave us the go ahead to backfill around the foundation after we put the drainage pipes back in place. Julie made us an amazing lunch to celebrate!

After lunch, Rob and I began installing the drainboard (CCW 6200) which goes on top of the waterproofing sheets. This layer consists of thick, dimpled, plastic sheets with a fabric on the outside (which allows water through) - water is supposed to come through the fabric and be routed down to the footing drains by the drainboard. This process required putting another layer of primer on the walls, in addition to priming the back of the drainboard sheets. The product manual actually recommended duct taping the sheets together to prevent soil from getting in during the backfill process. Rob finished putting up the drainboard this afternoon (Friday) and then I completed the process with the duct taping.


Duct tape - who knew?

This morning (Friday), Van's crew came to pour the concrete for the floor (slab). When I came down to the site around noon, we had a floor!

Rob in his workshop!





Rob had placed extra insulation between the slab and the walls, which will prevent a cold bridge

Finally, this afternoon/evening (Friday), Rob was able to get the drainage pipe back in and cover it with stone, and then I laid filter fabric on top (which will keep the soil from getting into the stone and drainage pipe). What an insane week!







Thursday, July 5, 2012

A Concrete Explanation - Updated

Part 1 - The Footings (concrete base of the building)
Cousins Judy and Lance arrived on Sunday in the midst of a crisis - Rob was digging the ditch for the footing that would go under the garage door and it began filling with water as he was digging. We called Van of Smith Brothers Concrete who was coming Monday morning to put in the footings to see what he suggested to do about the water - Van came over with his water pump, drained the water, and suggested that Rob dig a drainage hole to catch the water overnight, which could be pumped out in the morning. With Rob on the excavator and Lance in the ditch spreading stone, the ditch for the footing got dug and was ready to go.


A Precarious Moment on the Excavator




Monday morning Van and his crew came at 6:30 am to set the forms for the footings. By the time I got down to the site, all the forms were in for the footings.


This is the ditch for the footing below the garage.

Van's trailer with the footing forms - they have a trailer or truck with the forms for each part of the foundation.



In the afternoon, the concrete was poured into the forms for the footings and the footings were set. The concrete hardened overnight.




Note the sleeve in the footing for the septic pipe.
What is Lance doing now? CAPTION CONTEST

The next morning Van came to remove the forms and form/pour the small wall that goes under the garage (second and third pictures below).





Tuesday afternoon Rob and Lance laid the drainage pipe around the footings (both on the inside and outside) and we had 3/4" crushed stone delivered to form a layer under the pipe and then to cover it. Lance connected the drainage pipes into our drainage ditch.






Drainage Outside the Footings

Drainage Inside the Footings



The Site at the end of the day - ready for the walls!

 
Rob had also filled in the drainage hole (in the middle of the picture).



Part 2 - The Workshop Walls
At 6:30 am Thursday morning, Van and the crew arrived with the forms for the walls. I watched for the next three hours as Van, his brother, and three other guys set up the forms. Rob assisted with some of the rebar.


Van's brother dropped in the forms from this truck post.



Wire used to hold the rebar in place

Here's the rebar laid out for the extension - where the utility room and bathroom (upstairs) will go




Here they are forming the window on the west side


Installing the rebar for the corner

Rob met with the electrician Kurt to discuss installing the electric line

Behind Van is the space left for the garage door

Here are the forms for the window on the west side

View from the inside




The building inspector came at 11:30 am to inspect the forms for the walls, and then after lunch, many trucks arrived in order to pour the concrete into the walls. The pictures below show the cement trucks (there were three) and the concrete pump with a hose that allowed for pouring the concrete into the walls. Quite a set up!






An Odd Juxtaposition

The next morning, Van and the crew came to remove the forms and the walls were now standing. The pictures below show metal pieces throughout the concrete that were holding the forms in place. Lance used a crow bar yesterday to knock them off the outside, so we can apply the waterproofing tomorrow.